Les étapes du projet

  • 2nd semester

    2018

    Delivery of the Réfectoire’s new events space and of the 39 housing units for scholars.

  • Autumn

    2016

    The restoration begins, after the completion of archeological excavations (duration: 24 months).

  • June

    2016

    Archeological excavations begin. Duration: 3 months.

  • February

    2016

    The request for proposals for the rehabilitation is issued.

  • January

    2016

    Cleaning operations begin. Duration: 3 months.

  • December

    2015

    The contractor is notified that cleaning operations can begin.

  • March 28,

    2014

    Signing of the public works concession established by the City of Paris following the request for proposals. The RIVP takes over the management of the...