Delivery of the Réfectoire’s new events space and of the 39 housing units for scholars.
Category: Calendar
Autumn | 2016
The restoration begins, after the completion of archeological excavations (duration: 24 months).
June | 2016
Archeological excavations begin. Duration: 3 months.
February | 2016
The request for proposals for the rehabilitation is issued.
January | 2016
Cleaning operations begin. Duration: 3 months.
December | 2015
The contractor is notified that cleaning operations can begin.
March 28, | 2014
Signing of the public works concession established by the City of Paris following the request for proposals. The RIVP takes over the management of the Réfectoire.